Mar 29 2021 01:10 PM
HI,
in our PWA implementation we have some resources that appear with blank Capacity although they have max. units set to 100% and have project assignments. As this only happens to some resources it seems to be a bug ?) as I can't find anything different between the "null" Capacity resources and others.
Has this happened to anyone and if so how did you solve?!
Thanks in advance,
Rosie
Mar 29 2021 03:04 PM
SolutionHello @Rosalia Dias ,
Are the resources showing as null capacity part of a Team Assignment Pool? If so, this is expected as their capacity contributes to the overall Team capacity.
Paul
Apr 05 2021 01:04 AM
@Paul Mather yes they are! in that case I must remove from Team Assignment pool - I will do that. Thanks!
Mar 29 2021 03:04 PM
SolutionHello @Rosalia Dias ,
Are the resources showing as null capacity part of a Team Assignment Pool? If so, this is expected as their capacity contributes to the overall Team capacity.
Paul