Microsoft Project Detail Page

Copper Contributor

Hello All,

 

We have created a page with custom fields to add project information, with that we have a EPT created to create projects.

 

Recently we incorporated some changes and published a new EPT.

 

Now when we are creating projects, on the form to add project information by default it should show as blank but currently it is taking some default values.

 

Any one who has experienced they please help 

1 Reply

Hello @Harshad_Sarode ,

Are these lookup fields with default values added? If you have a default value set for a lookup table field, this is expected. See an example enterprise custom field setting here:

PaulMather_0-1677494882198.png

 

Paul