Hi,
I maintain a large program schedule (superset) in MS Project. The program has multiple contractors, each having their individual schedules (subset) & these schedule form a subset of the larger program schedule.
A large part of my work is to keep the program schedule (superset) in synch with contractor's schedule (subset). Even though the scope for contractor work remains the same, often new tasks, new relationships, etc. are created in contractor's schedule, which I need to integrate into program schedule. This is very manual and tedious process, where every task and its predecessor from contractors' schedule is mapped to program schedule. The end objective is to get the dates in program schedule align with dates in contractor's schedule.
Is there a more efficient way to merge these two schedules?
I tried copy pasting contractor's schedule into program schedule, but it messes up the program schedule and getting it right is a bigger problem than manually integrating contractor's schedule. I use Gantt Chart Format -> Task path -> Driving Predecessor but that still manual and does not show very accurately.
Nov 03 2022 05:10 PM
Nov 03 2022 05:45 PM
Nov 03 2022 06:33 PM
Nov 03 2022 06:49 PM
Nov 04 2022 08:36 AM