Mar 07 2021 05:48 AM
Hello,
We are upgrading the server from 2010 to 2019 (Project Pro 2016).
We noticed a task that has 2 resources - 1 work resource and 1 material resource.
We researched it in 4 places:
We see that the work resource assignment ends on 1-Sep-19 in all sources
We see that the material resource assignment ends on 29-Dec-19 in Pro 2010 and both DB's (meaning that the migration works OK)
We see that the material resource assignment ends on 1-Sep-19 (same date as the work resource) in Pro 2016, meaning that when the Pro is opened, it re-calculated the material assignment according to a different logic, maybe adjusting it to the work assignment. BTW - the total amount of material work didn't change, the entire material work performed for Sep - Dec in 2010 was summed up to 1-Sep-19 in Pro 2016.
Is there any explanation for this?
Thanks,
Barak
Mar 07 2021 08:48 AM
SolutionMar 08 2021 07:24 AM
Mar 08 2021 08:39 AM
Mar 07 2021 08:48 AM
Solution