Lead time not reflected in "Early Start"

%3CLINGO-SUB%20id%3D%22lingo-sub-2900170%22%20slang%3D%22en-US%22%3ELead%20time%20not%20reflected%20in%20%22Early%20Start%22%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-2900170%22%20slang%3D%22en-US%22%3E%3CP%3EI%20have%20built%20a%20schedule%20with%20predecessor%20links.%20I%20have%20added%20a%20FS-10%20day%20lead%20time%2C%20but%20it%20is%20not%20reflected%20in%20the%20Early%20Start%20column.%20The%20Early%20Start%20still%20shows%20the%20day%20after%20the%20predecessor%20finish.%20Any%20advice%3F%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EThanks%2C%3C%2FP%3E%3C%2FLINGO-BODY%3E
Occasional Visitor

I have built a schedule with predecessor links. I have added a FS-10 day lead time, but it is not reflected in the Early Start column. The Early Start still shows the day after the predecessor finish. Any advice?

 

Edit... I also changed Early Start to Start, and still no success.

 

Thanks,

1 Reply

@gary_wiley 

Does the Gantt Bar reflect the 10 day lead? Does the task have any other predecessors that may be holding it from starting earlier? And I assume the task has no constraints, right?

 

Is calculation set to automatic? Are all tasks auto-scheduled? Is any leveling applied?

 

A screen shot could be helpful.

John