Lead time not reflected in "Early Start"

Copper Contributor

I have built a schedule with predecessor links. I have added a FS-10 day lead time, but it is not reflected in the Early Start column. The Early Start still shows the day after the predecessor finish. Any advice?

 

Edit... I also changed Early Start to Start, and still no success.

 

Thanks,

1 Reply

@gary_wiley 

Does the Gantt Bar reflect the 10 day lead? Does the task have any other predecessors that may be holding it from starting earlier? And I assume the task has no constraints, right?

 

Is calculation set to automatic? Are all tasks auto-scheduled? Is any leveling applied?

 

A screen shot could be helpful.

John