Oct 29 2021 06:05 AM - edited Oct 29 2021 08:06 AM
I have built a schedule with predecessor links. I have added a FS-10 day lead time, but it is not reflected in the Early Start column. The Early Start still shows the day after the predecessor finish. Any advice?
Edit... I also changed Early Start to Start, and still no success.
Thanks,
Oct 29 2021 08:52 AM
Does the Gantt Bar reflect the 10 day lead? Does the task have any other predecessors that may be holding it from starting earlier? And I assume the task has no constraints, right?
Is calculation set to automatic? Are all tasks auto-scheduled? Is any leveling applied?
A screen shot could be helpful.
John