May 08 2022 11:54 PM
Hello guys,
does anyone met these issues before?
Project:
There is something wrong - when I try to filter table, filter applies but immediately the filter buttons disappear.. Also, when trying to switch to Task usage view, it doesn't work (doesn't switch the view). Of course I tried to copy original view from template, did not work. I tried to export XML data and import it into blank new project, did not work either.
Only way I could switch into that view is to open New window with that specific view.. but that's crazy, you know..
Any ideas? ;)
Thanks,
Milan
May 09 2022 05:00 AM
May 09 2022 05:11 AM
May 09 2022 07:54 AM
May 12 2022 01:42 AM
Hi John,
let me go through the checklist ;)
1) Tried on many different (2013/2016/2019) 32/64bit
2) Always Fully updated
3) English / Czech
4) Single file, local resources (removed work res. only material res. kept)
5) No inserted objects
6) Latest version 51.4MB
7) Yep, 8 calendars
8) Nope
9) Yep - text (11), number (6), outline number (5)
10) no VBA
When trying to import XML to new project, app crashes down with this event:
Cheers,
Milan
May 12 2022 08:02 AM
May 17 2022 05:55 AM
May 17 2022 07:53 AM - edited May 17 2022 08:38 AM
Milan,
Something else must be going on because method 3 should not lose custom fields and baseline data is carried over and is "active" (i.e. responds to earned value metrics).
What exactly is "lost" with respect to custom fields? If you are referring to custom fields that have been renamed then yes, that new name will not be carried forward, it's part of the custom formatting.
What exactly is "lost" with respect to baseline data?
John