Sep 14 2016 06:13 AM - edited Sep 14 2016 06:13 AM
Has anyone else seen lag defaulting to edays in Project 2016? It only happends when using the task information dialog to enter lag but then has to be edited in the cell/edit bar back to days. Most Frustrating! I've sent a frown.
Sep 15 2016 05:09 AM
Hi Sara
just tested and for me it keeps correctly "elapsed days" or "days" depending of what I typed into Lag-field. Tested with version: 16.0.4432.1000 32 bit...maybe it came with a later update.
Adrian
Sep 17 2016 09:23 AM
SolutionHi Sara - this is a known issue. See:
for some recommended work arounds.
Sep 18 2016 01:45 AM
Sep 17 2016 09:23 AM
SolutionHi Sara - this is a known issue. See:
for some recommended work arounds.