We have a customer who uses Office 2016. So we installed Project Professional 2016 for connecting to Project Online.
One of their users have problems to open a project from PWA to Project Professional 2016. When she opens a project from the Project Center in PWA to Project Professional 2016, she has the following message : “Sorry, we can't open the project. Please try again”.
I have verified these points :
Do you know how to solve this problem?
Apr 24 2023 10:03 AM
Hello @nicole50 ,
What is different for this user when compared with a user that works OK performing the same action? Both have Project Pro 2016 install using the same method? Both have the same version of other Office apps deployed? Could be an issue with a mismatch of MSI and C2R versions maybe?
Have you tried deleting the Project Web App account in MS Project (File > Info > Manage Accounts) then add a new one? You have to be connected to the MS Project Computer profile to do this.