I am using the Import Wizard to update two fields in my existing project using the Unique ID as a key. The two fields are both Textxx fields. When I import, I get
for every task and it either deletes all the start/finish/duration details (Yes) or just the duration and effort fields (no). I don't want MSP to touch these fields.
What can I do?
Thanks
Charles
Jan 13 2023 04:05 PM
Jan 14 2023 04:05 AM
Thanks for replying. Answers below. Charles
Version:
Import Wizard:
MS_Planner_ID is Text10
MS_Planner_Completed_Off is Text16
Grateful any help on this. An example of before and after is:
Before:
After (replying No to above dialog box)
Jan 14 2023 04:08 AM
Jan 14 2023 06:59 AM - edited Jan 14 2023 02:31 PM
Charles,
Thanks for the plethora of screen shots. Doing a quick overview, nothing pops out. I emulated your file and did a merged import. As expected everything works fine for me, only the custom text field was updated, nothing else.
Project test file:
Excel sheet:
Import map:
Final result in Project:
Would you be willing to share your Project and Excel files with me? It would make troubleshooting a lot easier. If you can share I'll give you my address.
John
Jan 15 2023 09:05 AM
Jan 15 2023 09:22 AM
Jan 24 2023 07:29 AM
Jan 24 2023 07:47 AM
Jan 24 2023 07:51 AM
Jan 24 2023 08:05 AM
Jan 24 2023 08:27 AM
Jan 24 2023 08:33 AM
Jan 24 2023 12:12 PM