Apr 27 2023 07:16 AM
I am struggling with something that should be simple:
In a custom Organization Field I need to put this formula:
iif(Csng([Lavoro])>0,(CSng([Costo]) / CSng([Lavoro]) * CSng([Lavoro Definitivo])),0)
[Lavoro] is like the standard field "Work" in English version
[Costo] is like the standard field "Cost" in English version
[Lavoro Definitivo] is a custom Organization field I created the tyoe of which is Cost.
The type of [Lavoro Definitivo] is Duration
It keeps telling me that the formula contains mistakes, but I really don't know what.
Without the IIf, the formula: (CSng([Costo]) / CSng([Lavoro]) * CSng([Lavoro Definitivo])) works fine.
The goal of it is to avoid the "#ERROR" in case [Lavoro]=0
Thank you
Apr 27 2023 08:31 AM
Thanks for clarifying your language terms with English terms. However, one part doesn't make sense. Namely, these statements:
[Lavoro Definitivo] is a custom Organization field I created the tyoe of which is Cost.
The type of [Lavoro Definitivo] is Duration
It says Lavoro Definitivo is both type Cost and type Duration. So which is it?
I put this formula in a test file and it results in no errors:
Cost1= IIf(csng([Work])>0,(csng([Cost])/csng([Work])*csng([Cost2])),0)
Also, which field did you customize with the formula (e.g. TextX, CostX, DurationX, etc.)?
John
Apr 28 2023 12:15 AM - edited Apr 28 2023 12:15 AM
Yes, John, my mistake.
[Lavoro Definitivo] is of type duration, being a "Work"
[Costo Definitivo] is of type Cost
Final Formula should be:
IIf (csng([Lavoro])>0, (csng([Costo]) / csng([Lavoro]) * csng([Lavoro Definitivo])), 0)
it didn't work, anyways, until I wrote the condition with the right blank characters in the right places...
IIf (csng([Lavoro]) > 0,......
it seems weird to me, but syntax has its rules, as far as I can see.
Thank you!