Howto work with large projects with many similar groups of tasks? Best practice

%3CLINGO-SUB%20id%3D%22lingo-sub-1208469%22%20slang%3D%22en-US%22%3EHowto%20work%20with%20large%20projects%20with%20many%20similar%20groups%20of%20tasks%3F%20Best%20practice%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-1208469%22%20slang%3D%22en-US%22%3E%3CP%3EHi%2C%3C%2FP%3E%3CP%3Ethis%20is%20the%20scenario%3A%3C%2FP%3E%3CP%3ETV-Production%20with%2050%20Episodes.%20Let's%20say%20every%20Episode%20contains%3A%3C%2FP%3E%3CUL%3E%3CLI%3EEpisode%201%3CUL%3E%3CLI%3EPreproduction%20(5d)%3C%2FLI%3E%3CLI%3EProduction%20(8d)%3C%2FLI%3E%3CLI%3EPostproduction%20(10d%3F)%3C%2FLI%3E%3CLI%3EDelivery%20(milestone)%20(0d)%3C%2FLI%3E%3C%2FUL%3E%3C%2FLI%3E%3CLI%3EEpisode%202%3C%2FLI%3E%3CUL%3E%3CLI%3EPreproduction%20(5d)%3C%2FLI%3E%3CLI%3EProduction%20(8d)%3C%2FLI%3E%3CLI%3EPostproduction%20(10d%3F)%3C%2FLI%3E%3CLI%3EDelivery%20(milestone)%20(0d)%3C%2FLI%3E%3C%2FUL%3E%3C%2FUL%3E%3CP%3Ea.s.o.a.s.f%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EAt%20the%20time%20of%20the%20project%20start%20we%20do%20not%20know%20how%20much%20time%20the%20Postproduction%20will%20take%20on%20average.%20So%20we%20assume%2010days.%3C%2FP%3E%3CP%3EQuestions%3A%3C%2FP%3E%3COL%3E%3CLI%3EEvery%20Episode%20has%20the%20same%20set%20of%20subtasks.%20How%20can%20I%20distinguish%20the%20tasks%20in%20teamplanner%3F%20Do%20I%20have%20to%20rename%20every%20subtask%20to%20make%20the%20name%20unique%3F%20(In%20most%20of%20the%20other%20Tables%20and%20views%20I%20can%20use%20the%20column%20%22summarytask%20name%22)%3C%2FLI%3E%3CLI%3EWhat%20if%20I%20want%20to%20change%20the%20duration%20of%20every%20%22Postproduction%22%20subtask%20because%20I%20notice%20that%20it%20takes%2015%20days%20on%20average%3F%20How%20would%20I%20do%20this%20(filter%20the%20tasks%20and%20drag'n'fill%20new%20durations%20or%20would%20you%20work%20with%20pasted%20links%20(paste%20special)%20in%20this%20cells%3F%20The%20latter%20seems%20a%20bit%20buggy%20to%20me%20in%20MS%20Project%202016.%20If%20I%20copy%20an%20Episode%20which%20contains%20pasted%20links%20it%20seems%20to%20be%20unreliable%2C%20some%20work%20some%20don't)%3C%2FLI%3E%3CLI%3EHow%20would%20you%20(the%20pros)%20prepare%20such%20a%20project.%3C%2FLI%3E%3CLI%3EIs%20it%20best%20practice%20to%20place%20the%20%22Delivery%22%20Milestones%20on%20the%20same%20hierarchical%20level%20as%20the%20Episodes%3F%26nbsp%3B%3C%2FLI%3E%3C%2FOL%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EI%20hope%20someone%20can%20push%20me%20in%20the%20right%20direction.%26nbsp%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EMany%20thanks%20in%20advance%3C%2FP%3E%3CP%3EBj%C3%B6rn%26nbsp%3B%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-LABS%20id%3D%22lingo-labs-1208469%22%20slang%3D%22en-US%22%3E%3CLINGO-LABEL%3E2016%3C%2FLINGO-LABEL%3E%3CLINGO-LABEL%3EProject%3C%2FLINGO-LABEL%3E%3C%2FLINGO-LABS%3E
New Contributor

Hi,

this is the scenario:

TV-Production with 50 Episodes. Let's say every Episode contains:

  • Episode 1
    • Preproduction (5d)
    • Production (8d)
    • Postproduction (10d?)
    • Delivery (milestone) (0d)
  • Episode 2
    • Preproduction (5d)
    • Production (8d)
    • Postproduction (10d?)
    • Delivery (milestone) (0d)

a.s.o.a.s.f

 

At the time of the project start we do not know how much time the Postproduction will take on average. So we assume 10days.

Questions:

  1. Every Episode has the same set of subtasks. How can I distinguish the tasks in teamplanner? Do I have to rename every subtask to make the name unique? (In most of the other Tables and views I can use the column "summarytask name")
  2. What if I want to change the duration of every "Postproduction" subtask because I notice that it takes 15 days on average? How would I do this (filter the tasks and drag'n'fill new durations or would you work with pasted links (paste special) in this cells? The latter seems a bit buggy to me in MS Project 2016. If I copy an Episode which contains pasted links it seems to be unreliable, some work some don't)
  3. How would you (the pros) prepare such a project.
  4. Is it best practice to place the "Delivery" Milestones on the same hierarchical level as the Episodes? 

 

I hope someone can push me in the right direction. 

 

Many thanks in advance

Björn 