Apr 11 2022 05:44 AM
Hi all,
Sometimes happens something like that:
- I set a link with the previus and following action
- I set a duration
- I force the end of the action (longer of the once previusly planned)
this is the diagram:
Is there any way to shift the bar at the beginning and having the connection line at the end rather than at the beginning of the action?
Thank you
Apr 11 2022 08:08 AM
May 02 2022 12:43 PM
May 02 2022 12:56 PM
Wow, where have you been for two weeks?
This example shows a 10 day lag on task c and a 2 day lag on the milestone.
John
May 02 2022 01:56 PM
May 02 2022 02:10 PM
Project has a Deadline field that can be used as a reference for a task or milestone. In this example all tasks are dynamic, allowing them free movement. The deadline shows graphically how close the finish milestone is to the deadline. Is that what you want? If not, please explain in more detail.
John