I have opened 7 projects in MSProjects cloud using enterprise resources.
6 out of these have been inserted in a main project.
Now I want to know list of tasks for each resource.
I tried the HELP links on this but I cannot see the list of tasks for each resourse across all projects. Earlier this was easily available under the Tab of Reports>Resources> who does what when.
PL let me know where I can get the list.
Oct 07 2022 07:50 AM
SolutionOct 07 2022 08:29 AM - edited Oct 07 2022 10:01 AM
@Dale HowardThx very very much Dale!! I did not know that all projects have to kept open. NOW I can see all tasks of resources.