How to find or how do we know who deleted the projects from project center or Delete Enterprise Obje

Occasional Contributor

Hi Team,

 

we had a incident happend in the production application, that is few projects are missed

 

We would like to know who deleted them.

Is there any way to find the deleted projects?

 

Please assist me.
@Paul Mather 

3 Replies
Murali --

You would need to look at the Queue to find this information, which will tell you the Owner of the Deletion job. Hope this helps.
Thank you for reply Dale,

Can you please elobrate more on this?
what do you mean by Queue .?
Where can i find the queue list..?

Thanks,
Murali

Hello @Murali_krishna_P ,

If you go to PWA Settings > Manage Queue Jobs - you can check the queue jobs there.

PaulMather_0-1648484807110.png

 

Paul