Hi all, I need to show Work in Days within the Project Center view under PWA (Project Online).
I found on some old TechNet forum a very old thread with the same question dated 2011 stating that this is not possible.
I wonder if in the last 10 years the problem has been resolved or if a workaround has been found out by someone. How do I show Work units in days within a "Project Center - Projects" view (whether it is a built-in view or a custom defined view)?
Thank you
Mar 19 2021 05:46 AM
Mar 19 2021 07:22 AM
Mar 19 2021 08:21 AM
Mar 19 2021 08:28 AM - edited Mar 19 2021 08:30 AM
I tried that. It does not work, unfortunately.
The project level custom field shows an empty cells column, the task level custom field is not available when defining the Project Center view.
Did I mess up something in my test? Do you confirm you can make it work?
Mar 19 2021 12:22 PM
SolutionMar 19 2021 12:23 PM
Mar 22 2021 07:19 AM
Thank you very much Dale!!!
The F9 did the magic. It was the step I was missing.
Now it works. Thank you again!