Apr 22 2022 01:58 AM
Gantt chart by default displays only duration and % complete data for a task. I have created a custom Number 1 column which calculates % time elapsed and comes in decimal. I then have a Text 1 col (say Planned % Complete) , which converts this decimal data into % value.
In gantt chart, it shows duration and % complete. I want Planned % Complete also to be shown in the gantt bar. How do I show this ?
I created a custom table, in which I added Number1 and Text 1 (i.e. Planned % Complete) columns. Then created a new view and linked the view with this custom table. In this new view, Gantt chart still shows duration bar and % complete bar. So how do I show Planned % Complete data as a bar in Gantt chart ?
Thanks,
Nk
Apr 22 2022 08:10 AM
Apr 24 2022 07:16 PM
Apr 24 2022 07:32 PM
Apr 24 2022 08:54 PM - edited Apr 24 2022 09:38 PM
Thanks John.
By changing row value as 2, I am able to get the 2nd bar. But when 2nd bar appears, the length of this 2nd bar is also the same as task duration. I'd like the length of this 2nd bar (say Planned % Complete bar) to be dictated by the Planned % Column (text field) value, just like the progress bar's length is dictated by % complete.
So, my Gantt chart should look like three bars
Duration bar - default, length controlled by duration field
Progress bar - default, length controlled by % complete field
Planned % complete bar - custom, length controlled by Planned % complete field.
How do I control the length of this 3rd bar ? If I select "To" as Complete Through, the length of the 3rd bar becomes equal to % complete and not Planned % Complete.
Any thoughts ?
Apr 25 2022 12:49 PM
SolutionApr 29 2022 06:55 AM
Apr 29 2022 08:14 AM