How to create a project list drop down in project online for a lookup table?

Occasional Contributor

Hi,

Instead of typing static data in lookup table in pwa.......Is it possible to get the dyanmic project names list in lookup table?. In the project details page,it has to show drop down project names.

Regards,

Anil.

2 Replies

Hello @Anil_kumar_Anakala ,

This is not possible out of the box, I wrote something that might give you a good start a few years ago. This can be seen on the following blog post: https://pwmather.wordpress.com/2018/05/24/projectonline-add-related-projects-to-a-custom-field-javas... If this is of interest I will find that solution starter code and upload it to my GitHub as the TechNet gallery is no longer available.

Paul

Thank you for your reply @Paul Mather . If you provide the code ,I will try to work on it.