How to change the weekend globally in project online timesheet page ?

Copper Contributor

Hi,

 

Earlier the timesheet weekend set to Fri-Sat, now i want to change it to Sat-Sun.

 

I can able to change for each projects but for the resource to fill the timesheet, the project online page still holding the Fri-Sat as weekend. Can somebody help me to change it?

 

Project_Alexa_0-1643872044378.png

 

2 Replies
Hi , were you able to change the timesheet weekend. I am having same concern , if you were able to change the weekend please let me know.

Try this. Go to Server Settings, under Time Management click Task Settings and Display and update the Week start on dropdown.