Apr 14 2022 08:46 PM
I have set up what I think is a relatively simple 2013 project using the default settings. I start with some manually scheduled milestones at the beginning followed by a bunch of auto-scheduled tasks. I have 5 people on a team, and each person can work any task so I set up one resource that maxes out at 500%.
I now need to see what the impact to the project end date would be if everyone worked 50 hours per week rather than the default 40. I go into Project Options - Schedule and change Hours per day and Hours per week to 10 and 50, respectively. The auto-scheduled task durations change as expected (i.e. a 5 day task reduces to 4 days), but the start and finish dates do not (they still represent the original 40hr/wk timeline). Also, after changing the default hours per day and week, if I go manually change the duration the start and finish dates no longer update like they did prior to changing the hours per day/wk. Any idea what happened and how I can get the desired result (which is to shorten the project length by working more hours)?
Apr 15 2022 08:23 AM
Apr 15 2022 10:11 AM
Hi John,
Thank you for the reply. I'm relatively new to Project so I'm kind of learning as I go. I used manually scheduled milestones to represent when data would be available for my team to begin working with. The dates for when the data become available are fixed and independent of the rest of the project. Is there a better way to represent this?
I didn't put anything in my description about creating a custom calendar because, well, I didn't create one. It sounds like that might be the missing link. I'll try creating one, applying it to the resource, and see if that works. Will report back if that solves my issues. Thank you for the tip!
Apr 15 2022 11:51 AM
Apr 15 2022 01:09 PM
Solution