Sep 13 2023 06:40 PM
I see features defined for project for web that indicate that milestones are supported. When I use bing chat and ask how to set a milestone in project for web I get instructions that indicate there should be a milestone checkbox on the information panel for a task. However, I don't see one. How do you set a task to be a milestone in project for web?
Sep 14 2023 06:08 AM
Hello @BradyGuyC18
Set the duration to be 0:
It sounds like Bing Chat is referring to Project Desktop / Project Online, not Project for the web.
Paul
Sep 14 2023 06:12 AM
SolutionSep 14 2023 06:12 AM
Solution