How do I filter projects' tasks available for Timesheet?

%3CLINGO-SUB%20id%3D%22lingo-sub-2235260%22%20slang%3D%22en-US%22%3EHow%20do%20I%20filter%20projects'%20tasks%20available%20for%20Timesheet%3F%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-2235260%22%20slang%3D%22en-US%22%3E%3CP%3EHi%20all%2C%3C%2FP%3E%3CP%3EI%20need%20to%20filter%20the%20projects%20that%20the%20timesheet%20is%20presenting%20to%20resources%20during%20timesheet%20compilation.%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EIf%20I%20have%20a%20project%20in%20draft%20or%20not%20yet%20started%2C%20I%20need%20to%20filter%20it%20in%20the%20possible%20tasks%20a%20resource%20can%20charge%20time%20on.%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EIs%20it%20possible%20to%20prevent%20timesheet%20from%20presenting%20tasks%20of%20a%20certain%20project%20%3F%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EThank%20you.%3C%2FP%3E%3C%2FLINGO-BODY%3E
Occasional Contributor

Hi all,

I need to filter the projects that the timesheet is presenting to resources during timesheet compilation.

 

If I have a project in draft or not yet started, I need to filter it in the possible tasks a resource can charge time on.

 

Is it possible to prevent timesheet from presenting tasks of a certain project ?

 

Thank you.

1 Reply
Paolone67 -- To the best of my knowledge, there is no way to filter the tasks shown on a user's Timesheet page to restrict the list to only a specific list of projects. By default, the Timesheet page automatically displays ever current task from every project. Sorry, but hope this helps.