How do I filter projects' tasks available for Timesheet?

Copper Contributor

Hi all,

I need to filter the projects that the timesheet is presenting to resources during timesheet compilation.

 

If I have a project in draft or not yet started, I need to filter it in the possible tasks a resource can charge time on.

 

Is it possible to prevent timesheet from presenting tasks of a certain project ?

 

Thank you.

1 Reply
Paolone67 -- To the best of my knowledge, there is no way to filter the tasks shown on a user's Timesheet page to restrict the list to only a specific list of projects. By default, the Timesheet page automatically displays ever current task from every project. Sorry, but hope this helps.