how do I export projects from project landing page https://project.microsoft.com/en-US/

Copper Contributor

Hi,

I could not see the export option on available on landing page of Project online https://project.microsoft.com/en-US/ it only shows web/online version of project file, is there any chance or way we can retrieve all tasks under the web/online version of project and export or import to Project Desktop?

please see attached image for your reference

 

Many thanks 

2 Replies
best response confirmed by erkindunya (Copper Contributor)
Solution

Hello @erkindunya ,

Projects created in Project for the web-  those that appear as "Project" in the Type column can't be exported / opened in Project Desktop. What's the reason for wanting to open in Project Desktop? See if there is already an idea here: https://microsoftproject.uservoice.com/forums/914203-project-for-the-web / raise a new suggestion for it.

Thanks

Paul

@Paul Mather  Many thanks for your promote response and information provided.

1 best response

Accepted Solutions
best response confirmed by erkindunya (Copper Contributor)
Solution

Hello @erkindunya ,

Projects created in Project for the web-  those that appear as "Project" in the Type column can't be exported / opened in Project Desktop. What's the reason for wanting to open in Project Desktop? See if there is already an idea here: https://microsoftproject.uservoice.com/forums/914203-project-for-the-web / raise a new suggestion for it.