Hello.
How can I catch opening project for reading in MS Project from PWA?
BR, Vasily
Jul 14 2021 12:16 AM
Jul 14 2021 12:41 AM
Jul 14 2021 02:26 PM
SolutionHello @Vasily_Zaytsev ,
I don't believe this will be possible as there are no events available for Project opening or project checked out - see the list of project events here https://docs.microsoft.com/en-us/previous-versions/office/project-class/jj231686(v=office.15)
For the full event details see: https://docs.microsoft.com/en-us/previous-versions/office/project-class/gg177847(v%3Doffice.15)
Paul