Jul 15 2021 12:29 AM
Jul 15 2021 05:56 AM
SolutionHello @Vasily_Zaytsev ,
The Project Server security groups, the groups used when in the Project permission mode, are not available in CSOM unfortunately, they are available in the PSI though.
Paul
Aug 18 2021 05:52 AM