Aug 30 2024 01:04 AM
i need to update my project, using already make template. when i update the predecessor, my date didn't change. anyone know why? i suspect this template is locked (maybe). anyone can help me?
Aug 30 2024 06:37 AM
Aug 31 2024 12:56 PM
Sep 01 2024 08:13 PM
long story is, i am a sub-contractor. the m.project file i got from main contractor. i need to do scheduling based on main contractor progress work. so i add my task on main contractor m.project file. when i want to update the predecessor (based on main contractor progress), my task's date didn't update as the predecessor task i set.
Sep 02 2024 09:16 AM
Unfortunately your "long story" didn't answer any of my, or Dale's, questions. What version of Project are you using? Are the tasks manually scheduled and if so, why? How exactly are you updating progress?
And a couple more questions to be answered. Is calculation set to "on"? Do the tasks have constraints?
A screen shot would help.
John