Still struggling with this ... Is it possible to show and print a Gantt of tasks associated with a specific resource?? I would like to do this from a master schedule.
For example, I would like to see a Gantt of tasks in all projects in the Master Schedule assigned to only welders over a few months. Is this even possible? For me this is important to help with shop loading, by seeing how the resources are allocated and when the tasks are scheduled to start and stop.