Gantt: Calendar Start

Copper Contributor

I am trying to get the timescale to begin directly beside the last column in the table. I have changed my project start date to ensure that it is correct. I have also adjusted the timescale several times. Project.png

3 Replies
best response confirmed by Dale Howard (MVP)
Solution
EthanSix,
I don't know of any way to always make the first Gantt bar start right at the beginning of the Gantt display, but here's what you can do. Select the earliest task or summary line and go to, Task > Editing group > Scroll to task. That won't bring the bar over to the vertical divider but it will bring it to a convenient location.

Hope this helps.
John

Thank you @John-project for the reply and help.

 

Thanks,

 

Ethan

Ethan,
You're welcome and thanks for the feedback.
John
1 best response

Accepted Solutions
best response confirmed by Dale Howard (MVP)
Solution
EthanSix,
I don't know of any way to always make the first Gantt bar start right at the beginning of the Gantt display, but here's what you can do. Select the earliest task or summary line and go to, Task > Editing group > Scroll to task. That won't bring the bar over to the vertical divider but it will bring it to a convenient location.

Hope this helps.
John