May 20 2021 03:14 PM
Understanding that when you assign a deadline to a task, that if the scheduled finish is later than the deadline, MSP calculates the total slack for that task and its predecessors as the difference between the scheduled finish and the deadline. Is there a way to keep this from occurring OR any 'Finish Variance'-esq type field to keep the total slack calculation based on the scheduled 'Finish Date' and not adjusting to the Deadline' date if the scheduled finish is later than the deadline?
May 21 2021 12:59 AM
May 23 2021 02:33 PM
May 23 2021 11:41 PM
SolutionMay 23 2021 11:41 PM
Solution