May 24 2023 05:38 AM
Hi all,
I would like to know if it is possible to exclude a resource from leveling in Microsoft Project 2021.
I have a supervisor who takes care of sending the parts to suppliers who will work on them. I want to keep the supplier's working time for the task, but the supervisor can send 2-3 at the same time to different suppliers (or the same) and does not have to wait for one to come back to start another (like other team members) .
Thank you for your help !
May 24 2023 06:48 AM
Yes you can keep tasks for one or more resources from being leveled. Assuming you are using the stand alone desktop version of Project, you should see these options:
Hope this helps
John
May 24 2023 01:03 PM
May 24 2023 01:28 PM