Dec 25 2021 12:50 AM
I need the forum help.
what is the best way to take "cost" resource into the EVM calculation?
Once allocating cost to an activity, it does take it into the BCWS- the total cost of the activity.
Yet, I don't see it under PV calculation, EV calculation or even AC calculation, even if the "cost" is designated as a "start" payment.
How to allocate the "cost" so that it will be calculated according to project status?
Tnx
Dec 30 2021 05:33 AM
Jan 06 2022 08:54 AM
Tnx a lot! wonder why it is so.
Fixed cost is an option, yet the crulling costs are not as needed with the EV, at least according to what I have done.
Jan 06 2022 02:19 PM