Oct 02 2023 04:47 PM
Hi there,
i define 5 activities FS, and entered cost directly, I mean no resources defined, so if you insert fixed cost field you will see values in fixed cost field,
I changed “actual cost calculated by MS project” to “actual cost entered manually”.
then I set baseline, and entered %complete & physical %complete, and entered actual cost manually, so BCWS was calculated after setting Baseline and is based on it.
the problem is that, after actuals I decided to set second baseline (baseline1) and called “baseline1 cost” , and set earned value baseline on “baseline1” and amazingly the BCWS is calculated unusually and for 100% task in %complete, BCWS is “actual cost + fixed cost”.
please check it with cost only with fixed cost, and actual cost manually, and set second baseline to find out BCWS.