Hey,
Can I add in MS Project to the network diagram the 4 times for any activity?
I mean: earliest start time, latest start time, earliest finish time and latest finish time
thanks
Dec 29 2022 12:07 PM
SolutionYou mean something like this?
If so, select the Network Diagram view and then go to, Network Diagram Format > Format group > Format Box Styles. From there create your own template with the desired fields such as I've shown here: Note, for the label to show, click the "show label in cell box". For the data to show, do not click that box. (That may seem obvious but it took me a few minutes to figure out the "decoder key").
Hope this helps.
John