EST, LST, EFT AND LFT

New Contributor

Hey,

Can I add in MS Project to the network diagram the 4 times for any activity? 

I mean: earliest start time, latest start time, earliest finish time and latest finish time

 

thanks

Guy0956_0-1672329298604.png

 

3 Replies
best response confirmed by Dale Howard (MVP)
Solution

@Guy0956 

You mean something like this?

2022-12-29_12-59-59.png

If so, select the Network Diagram view and then go to, Network Diagram Format > Format group > Format Box Styles. From there create your own template with the desired fields such as I've shown here: Note, for the label to show, click the "show label in cell box". For the data to show, do not click that box. (That may seem obvious but it took me a few minutes to figure out the "decoder key").

2022-12-29_13-04-04.png

Hope this helps.

John

@John-project 

 

Thank you John!!

You helped me a lot 

Guy0956,
You're welcome and thanks for the feedback.
John