Equalizing task duration and project duration

%3CLINGO-SUB%20id%3D%22lingo-sub-2222979%22%20slang%3D%22en-US%22%3EEqualizing%20task%20duration%20and%20project%20duration%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-2222979%22%20slang%3D%22en-US%22%3E%3CP%3EHi%2C%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EI%20need%20to%20create%20a%20task%20(Project%20Management%20task)%20that%20should%20automatically%20equal%20the%20entire%20project%20duration%2C%20whatever%20task%20modification%20may%20impact%20on%20the%20total%20duration%20of%20my%20project.%3C%2FP%3E%3CP%3ECurrently%2C%20every%20time%20I%20change%20a%20task%20that%20shifts%20the%20project%20finish%20to%20a%20later%20date%2C%20I%20have%20to%20manually%20extend%20as%20well%20my%20%22Project%20Management%20task%22%20to%20match%20the%20entire%20project%20duration.%20Is%20there%20a%20way%20to%20automatize%20this%20behavior%3F%3C%2FP%3E%3CP%3EThank%20you.%3C%2FP%3E%3C%2FLINGO-BODY%3E
Occasional Contributor

Hi,

 

I need to create a task (e.g. "Project Management task") that should automatically equal the entire project duration, whatever task modification may impact on the total duration of my project.

Currently, every time I change a task that shifts the project finish to a later date, I have to manually extend as well my "Project Management task" to match the entire project duration. Is there a way to automatize this behavior?

Thank you.

1 Reply
We got you covered. What you want is called a hammock task. Take a look at this Wiki article on how to create it:
https://social.technet.microsoft.com/wiki/contents/articles/32040.ms-project-hammock-tasks.aspx
John