Equalizing task duration and project duration

Contributor

Hi,

 

I need to create a task (e.g. "Project Management task") that should automatically equal the entire project duration, whatever task modification may impact on the total duration of my project.

Currently, every time I change a task that shifts the project finish to a later date, I have to manually extend as well my "Project Management task" to match the entire project duration. Is there a way to automatize this behavior?

Thank you.

1 Reply
We got you covered. What you want is called a hammock task. Take a look at this Wiki article on how to create it:
https://social.technet.microsoft.com/wiki/contents/articles/32040.ms-project-hammock-tasks.aspx
John