Hi there,
I have enterprise custom fields loaded into projects I have created using the desktop application and have published it to PWA. However, when I look at my tasks in PWA with a custom view including the enterprise custom fields, it doesn't seem to pull through the same information on the desktop app. See below:
I have re-published from the desktop app a few times, with no change
Why would this be?
Sep 12 2022 08:53 PM
Hi @BlissL,
The created enterprise custom fields doesn't have any issue as it a Task level field and I believe you are able to find view values in it when viewing the schedule.
However, the task page shows assignment of an resource (user). So, please add values at assignment level by opening project in desktop app and using Task Usage view.
Give similar value against resource name also and then it will be reflected in Task page. Sure, it will work this time.
Thanks,
RatanPushp