Aug 09 2024 05:25 AM
I have created a resource Enterprise Custom Field called "Role". The new field shows up on the "Edit Resource" page in PWA. I populate the field with a value (it is a text lookup type using the "Role" lookup table). When I open the resource in Project Desktop, the field is there, but the value I entered in PWA is not there. It is just empty. If I update the value in the Desktop, it stays. Why is the value not showing up in the desktop when I populate through PWA?
Aug 10 2024 06:57 AM
SolutionHello @David_Howe ,
If you edit / update in PWA with MS Project desktop closed. Then launch MS Project Desktop, is the data then correct in MS Project Desktop?
Paul
Aug 12 2024 04:40 AM
Aug 12 2024 04:52 AM
Happy to help, glad it is sorted @David_Howe ,
Please can you mark my reply as the best response so it helps others who might have the same issue.
Thanks
Aug 10 2024 06:57 AM
SolutionHello @David_Howe ,
If you edit / update in PWA with MS Project desktop closed. Then launch MS Project Desktop, is the data then correct in MS Project Desktop?
Paul