Hello
I have resources and each resource has a number of workers available per day
for example, a laborer has std. rate 10$/hr and the total number available per day is 4
for 1st activity, the number needed is 3 laborers
how can I add these to the Microsoft project
I added the resources in the resource sheet but the availability per day I don't know how to add them since the cost will be different