Mar 03 2023 06:33 AM
Is there any way in project for the web to split a task out by effort per resource. For example:
Task A = 100 Hours in Total
3 Resources applied, but Resource A = 80% of the effort, Resource B = 10% of the effort, and Resource C = 10% of the effort?
The idea is to provide a resource planning tool within Power Bi to illustrate the time planned on projects.
Mar 03 2023 07:54 AM
Mar 03 2023 08:15 AM
@Paul Mather thanks for this, however i cannot seem to find an assignments view on my version of Project. Is this not released yet?
Mar 03 2023 10:40 AM