Effort Per Resource

Copper Contributor

Is there any way in project for the web to split a task out by effort per resource. For example:


Task A = 100 Hours in Total

3 Resources applied, but Resource A = 80% of the effort, Resource B = 10% of the effort, and Resource C = 10% of the effort?

 

The idea is to provide a resource planning tool within Power Bi to illustrate the time planned on projects.

3 Replies

Hello @PaulKing2224 ,

You can allocate specific hours per resource using the assignments view:

PaulMather_0-1677858814961.png

 

https://pwmather.wordpress.com/2023/02/28/assignments-view-in-projectfortheweb-projectmanagement-wor... 

Paul

@Paul Mather  thanks for this, however i cannot seem to find an assignments view on my version of Project. Is this not released yet?

 

d.JPG

Hello @PaulKing2224 ,

It's rolling out now so you should see it very soon!

Paul