May 25 2023 03:20 PM
HELLO COMMUNITY,
I REQUEST HELP WITH THE FOLLOWING.
I MADE A BUSINESS TEST GANTT, BUT IN THE SCHEDULE IT SHOWS ME THAT THE PROJECT IS 20% COMPLETE AND HAS A DURATION OF 4 DAYS, BUT IN THE PROJECT SUMMARY IT DOES NOT SHOW ME THIS INFORMATION.
HOW CAN I SOLVE THAT?
May 25 2023 07:06 PM - edited May 25 2023 07:19 PM
fgonzales515,
First of all you do not need to shout (i.e. all caps), it will not get you a quicker or better answer.
What version of Project are you using? It looks like your second screen shot shows the Gantt Chart view of Project desktop but I don't quite understand what the first screen shot is showing. What view is that?
Did you insert the file into a master and that is what is showing in the first screen shot?
John
May 26 2023 06:19 AM
I'm using Project Online.
Both captures correspond to Project Online.
The first is Projects Portfolio and the second capture is Gantt Diagram.
I don't know if I understand my query.
In the Gantt Diagram I have a duration of 4 days and 20% Complete, but in the Project Portfolio it does not show me the same.
May 26 2023 07:36 AM