Display Notes

Occasional Visitor

Hi All, I am hoping you can help. Is there a way to display the notes in project as comment bubbles or something similar without having to hover over the note similar to the comment bubbles in word? I have clarifying information that I would like to permanently display on a task without having to hover over the note sticky. Thanks

1 Reply
Mdevin57,
Sorry, no can do with the "bubble" idea. If the note text is less than 255 characters and has no line feeds then you can add the Notes field as a column in the view. However, if your notes are longer than 255 characters and/or have line feeds the only way to view them is via the Notes tab of the Task Information window.

Hope this helps.
John