Oct 12 2022 11:01 AM
Hello,
I am having an issue where some of my desktop projects are not importing to Project Online. Some files imported without issues, but others will not. I saw an earlier post about this but there was no answer on how to fix the issue, just that it was fixed. Any direction or assistance is appreciated.
Desktop Version: Microsoft® Project® Online Desktop Client MSO (Version 2202 Build 16.0.14931.20704) 64-bit
Message: Correlation ID: 1328838d-274b-43bd-a20f-42e4d4671e45
Oct 12 2022 11:27 AM
I don't have Project Online but from your version description it looks like your installation hasn't been updated for some time. I suggest you check for updates and install them.
Joh
Oct 12 2022 12:56 PM
Oct 12 2022 01:17 PM
Oct 12 2022 01:34 PM
Oct 13 2022 06:41 AM
Hi,
It didn't work when I cleared the baseline in the original project file. But I did the export to Excel and imported into a new project and then uploaded it and it worked. There must be some setting in these original files that is just not compatible that is being cleared by this export/import process. I only have a few of these projects so the manual process is not too cumbersome.
Oct 17 2022 02:53 PM
Oct 18 2022 04:23 AM
Oct 18 2022 05:16 AM
Oct 18 2022 08:31 AM