Deleted Project Gantt chart web part

Copper Contributor

Hi,

I mistakenly deleted Project Gantt Chart web part on the Project Schedule page in Project Server 2016. How can I add it back?

 

1 Reply
best response confirmed by Dale Howard (MVP)
Solution

Hello @nooruls143,

Access the Schedule Project Detail Page (PDP), click the Page tab > Edit Page > Add a web part > Select "Project Web App" from the Categories section > Select "Details in the Parts sections > Click Add > Stop Editing.

That should then add the schedule web part back on the page.