Sep 08 2022 07:21 PM
Hi there,
I am currently trying to link some sub-projects as part of a master project, and am following the instructions in the below screenshot after a quick google.
However, this file syntax doesn't seem to be working and I keep getting this error. I have tried the filename with and without .mpp on the end with the same results.
Sep 09 2022 05:17 AM
SolutionSep 19 2022 09:38 PM
@Dale Howard Thank you, I just have another query off the back of that -
Another question - I have created project schedules for each stage of the NPD process - i.e., separate file for Scoping, separate file for Development, separate file for Production Execution
I have been using the linked instructions to link these projects together into a master project file, and I have saved this temporary master project as a template file called "Local Manufacturing".
We have many different project types so I've created another 'master template file' called Import FOB, which uses the same Scoping file as in "Local Manufacturing" but a different Development & Production Execution file. I have again linked these projects together and saved the temporary master project.
I've tried to create another template master file, but now it's giving me errors. Do I need to resave all the project files as templates and then create the "master files"? Would what I'm doing actually work?
Thank you in advance!
Sep 20 2022 05:29 AM
Sep 09 2022 05:17 AM
Solution