Jan 01 2023 06:12 AM
Hi All
I can see that P4W does not support Critial Path What is Project for the web? - Microsoft Support, but I can see Critial Path by enable this option as picture
Thanks in advance
Truong Dai
Jan 01 2023 02:04 PM
Jan 01 2023 06:43 PM
Jan 02 2023 06:17 AM
Hey @daibt,
To add to this, the Critical Path feature in P4W is available for users with Project Plan 3 or higher: https://learn.microsoft.com/en-us/office365/servicedescriptions/project-online-service-description/p...
Paul
Jan 02 2023 11:43 PM
Thanks for your document, that help me to make sure that Project Plan 3, 5 support Critical Path only
Jan 03 2023 02:36 AM
You're welcome @daibt , please mark a response as the answer when you get a chance so that it helps others.