Oct 07 2021 02:55 PM
Hello all, first time posting a question here and i appreciate any help!
So, my company wants to use microsoft project not to track task durations or schedule, but to assign manpower (employees personel etc,) to a given area. The areas are broken down by the general contractor, and we wouod use their format for location and duration per location, to come up with our own schedule; how many people are needed per area, and per contractors given duration to us.
i.e:
Contractor's original schedule says:
Area A - Framing walls - 5 days given to complete the task.
Internally: Area A has been estimated to take 10 days - So manpower needed are 2 people in that area to complete within 5 days - 10 days/man divided by 5 days = 2 men
My question is, how can i alter my schedule, and in my resource usage view, to show this information? Currently my resource usage shows me the areas, but it also shows me "hours" instead of number of men.
Oct 08 2021 08:41 AM