Controlling Notifications in project for the web plans

Copper Contributor

i am trying to control the notifications sent to the project team on the plan level in project for the web but i don't find any option to edit the notifications in the plan settings view as attached. 

 

So what should i do?

notifications.png

6 Replies
moazsafwat --

I am not aware of any way to edit the notifications that are sent by Project for the Web. Sorry, but hope this helps.
I am sorry Dale, but this reply doesn't help.
It is unacceptable to bother and distract a big team in a project with every action and progress on the plan. we need to send notifications only to the assigned persons regarding their assigned tasks.
So anyway please to let the development team to add this feature soon?

I really appreciate any help you can provide.
moazsafwat --

I do not work for Microsoft, so I have no control or input over what features the product development team offers in Project for the Web. I am simply a volunteer in this forum. I can understand your pain, but there is nothing I can do about it. Sorry.
best response confirmed by Dale_HowardMVP (MVP)
Solution

@moazsafwat There is no global setting at this time a project manager or admin can set to disable notifications.  However, each resource can manually opt out of notifications by disabling them as shown below by going to the Project Home page, https://project.microsoft.com/, then follow the steps below.

RodFromm_0-1726096761939.png

 

 

Thank you Mate for the hint
1 best response

Accepted Solutions
best response confirmed by Dale_HowardMVP (MVP)
Solution

@moazsafwat There is no global setting at this time a project manager or admin can set to disable notifications.  However, each resource can manually opt out of notifications by disabling them as shown below by going to the Project Home page, https://project.microsoft.com/, then follow the steps below.

RodFromm_0-1726096761939.png

 

 

View solution in original post