Consecutive task

Copper Contributor

Hi,
I have a task that I want to be performed consecutively, so if there’s a holiday in the middle, the software will postpone the beginning of the task to the next day when it can be performed continuously.
How do I do this? 

3 Replies
eyalk2300 --

Which tool are you using? Microsoft Project desktop or Project for the Web? Let us know and we will try to help you.
Microsoft Project desktop
eyalk2300 --

You will need to edit the Standard calendar so that includes the holdiay you mentioned. Refer to the following YouTube videos on how to edit the Standard calendar:

https://youtu.be/GrR8v1Y4RN0
https://youtu.be/UOCuJdC9Oqc

Hope this helps.